NEW QUESTION # 55
What is the role in an eXtreme Programming (XP) project that ensures the right project processes are applied?
- A. Domain Expert
- B. ScrumMaster
- C. Product Owner
- D. Coach
Answer: D
Explanation:
Explanation/Reference:
NEW QUESTION # 56
DRY is an acronym for which Agile development principle?
- A. Don't Repeat Yourself
- B. Develop, Refactor, Yagni
- C. Deploy Repeatedly
- D. Development Requires You
Answer: A
NEW QUESTION # 57
In eXtreme Programming (XP), analysis, design, coding, and testing phases are done:
- A. In sequence.
- B. Every day.
- C. At the beginning of the iteration.
- D. Without documentation.
Answer: B
Explanation:
Explanation/Reference:
Explanation:
NEW QUESTION # 58
What is the first thing that a team should do to estimate user stories for a project?
- A. Schedule a team meeting to understand them.
- B. Define the story points measure.
- C. Sort the user stories according to priority.
- D. Estimate through function point analysis.
Answer: B
NEW QUESTION # 59
When an Agile project team receives an "emergency request" during an iteration, which is the best first step that the Agile project manager should take?
- A. Provide the customer with options provided by the project team.
- B. Explain that the team cannot do the added work until the next iteration.
- C. Stop work on unfinished user stories and work on the urgent request.
- D. Call a team meeting and change the iteration scope to include the request.
Answer: A
Explanation:
Explanation/Reference:
NEW QUESTION # 60
Continuous integration ensures that a product is:
- A. Delivered for testing at the end of each day.
- B. Ready to ship when all features are complete.
- C. Deployed after final business approvals.
- D. Technologically ready to deploy at any time.
Answer: D
NEW QUESTION # 61
Pick 5 activities that are the responsibilities of the development team in Scrum.
Answer:
Explanation:
NEW QUESTION # 62
In Agile projects, the technique in which planning is done at three distinct horizons is known as:
- A. Portfolio Management.
- B. Monte Carlo Analysis.
- C. Progressive Elaboration.
- D. DelphiTechnique.
Answer: C
Explanation:
Explanation/Reference:
NEW QUESTION # 63
Exhibit:
Based on me burndown chart, what is the iteration's status?
- A. It trended ahead of schedule and completed everything on time
- B. It trended behind schedule and did not complete everything on time
- C. It took less time than expected and had to be shortened
- D. It took more time than expected and had to be lengthened
Answer: B
NEW QUESTION # 64
An agile team is planning the tools they will use for the project. They are debating how they should show what work is in progress. Of the following options, which tool are they most likely to select?
- A. Product roadmap
- B. Work breakdown structure
- C. Task board
- D. User story backlog
Answer: C
NEW QUESTION # 65
Which one is NOT a level of need in the Kano Model?
- A. Excitement Needs
- B. Performance Needs
- C. Basic Needs
- D. Enabling Needs
Answer: D
NEW QUESTION # 66
Continuous integration ensures that a product is:
- A. Delivered for testing at the end of each day.
- B. Ready to ship when all features are complete.
- C. Deployed after final business approvals.
- D. Technologically ready to deploy at any time.
Answer: D
NEW QUESTION # 67
A newly formed scrum team wants to foster an environment of transparency and experimentation. The team decides to use a Kanban board to record and track encountered impediments. Emphasis is placed on how issues are resolved and the strategies for preventing them in the future.
Over time, what will be the result of this approach?
- A. Key performance indicators (KPIs)
- B. Specific, measurable, assignable, realistic, and time-based (SMART) goals
- C. Kaizen
- D. Muda
Answer: C
Explanation:
Explanation/Reference: https://www.digite.com/kanban/what-is-kanban/
NEW QUESTION # 68
In the Lean process, the focus is on:
- A. Optimizing completed work across the process stream.
- B. Using the optimal resources.
- C. Cross training the team to eliminate bottlenecks.
- D. Managing team efficiency.
Answer: A
NEW QUESTION # 69
Drag and Drop Question
The Agile Manifesto states we value some items over others. Match the items in the columns below so each item on the left is valued over the corresponding item on the right.
Answer:
Explanation:
NEW QUESTION # 70
Who is responsible for prioritizing the stories that will be included in the iteration?
- A. Developer
- B. Product Owner
- C. ScrumMaster
- D. Team
Answer: B
NEW QUESTION # 71
During project inception an agile practitioner engages the stakeholder to ensure alignment on the project's strategy and vision The stakeholder asks for detailed requirements design, and delivery plans What should the agile practitioner do?
- A. Set expectations regarding the appropriate level of details requested during this stage
- B. inform the stakeholder mat no detailed documents are provided using agile practices
- C. Provide all information requested by the stakeholder
- D. Ask the team to supply the information 10 the stakeholder
Answer: A
NEW QUESTION # 72
Drag and Drop Question
Match the definitions (on the right) to each of the characteristics of a good User Story (on the left).
Answer:
Explanation:
NEW QUESTION # 73
Which of the following techniques best encourages osmotic communication?
- A. Reviewing requirements frequently with the Product Owner
- B. Inviting the customer to attend every iteration demo
- C. Having the Product Owner attend daily standups
- D. Seating the team members together in a work area
Answer: D
NEW QUESTION # 74
Outing a review session a customer representative is concerned that a story fails to satisfy the scope of work. However the product owner declares that the scope of work is complete What should be done with this story?
- A. Discard it and create a new story for the remaining scope of work
- B. Mark it as complete, since the product owner has the final say
- C. Mark it as incomplete and prioritize it for the next sprint
- D. Mark it as complete, since the team completed the scope of work
Answer: D
NEW QUESTION # 75
The team estimation game method mainly consists of a:
- A. Brainstorm session where resources are related to prioritized work packages.
- B. Pile of cards with user, capability, and value to be prioritized by the project team.
- C. Spreadsheet with backlog issues to be prioritized and each to be given a prioritizationnumber.
- D. White board session where iterations are estimated and related to the project road map.
Answer: B
Explanation:
Explanation/Reference:
Explanation:
NEW QUESTION # 76
Drag and Drop Question
Match the traditional contract model of the left with the Agile alternative on the right.
Answer:
Explanation:
NEW QUESTION # 77
What is the common communication bridge between the team and the Product Owner?
- A. Sprint release plan
- B. Burndown chart
- C. Product Backlog
- D. Scrum team meeting
Answer: C
NEW QUESTION # 78
......
What to Expect
The PMI-ACP test is multiple-choice and consists of 100 scored items and 20 pretest questions. The vendor does not reveal the unscored items and randomly distributes them throughout the test. The time allotted for candidates to complete the exam is three hours. In all, applicants will answer questions from seven domains like Agile Principles and Mindset (16%), Value-driven Delivery (20%), Stakeholder Engagement (17%), Team Performance (16%), Adaptive Planning (12%), Problem Detection and Resolution (10%), and Continuous Improvement (9%). In addition, examinees can prepare for and take the official exam in English, Arabic, Japanese, Korean, Portuguese, and Spanish. Finally, the test fee is $435.00 for PMI members and $495.00 for non-members.
Updated Test Engine to Practice PMI-ACP Dumps & Practice Exam: https://prepaway.vcetorrent.com/PMI-ACP-valid-vce-torrent.html