About Microsoft 074-343 Exam

The 074-343 exam has a reputation for tripping up even experienced professionals. VCETorrent breaks the Microsoft Managing Projects with Microsoft Project 2013 syllabus down into 110 practice questions with clear explanations, so tricky topics stop feeling intimidating.

Microsoft 074-343 Exam Syllabus Topics:

SectionObjectives
Manage Resources and Assignments- Manage resource allocations and assignments
- Enter and edit resource information
Track and Analyze a Project- Update and compare project progress
- Set and maintain baselines
Create a Task-Based Schedule- Build logical schedule with dependencies
- Define project information and task structures
Communicate Project Information- Customize views and reports
- Share data with other applications and SharePoint
Initialize a Project- Set up calendars and custom fields
- Create a new project and templates

Microsoft Managing Projects with Microsoft Project 2013: Common Questions From Candidates

The Microsoft Managing Projects with Microsoft Project 2013 exam (code: 074-343) is the official Microsoft exam that leads to the Microsoft Project certification. It sits at the Specialist level of the Microsoft certification track. It is also connected with related credentials such as Microsoft Certified Professional (Historical). Passing it proves to employers that your skills have been validated by Microsoft itself, which is why the 074-343 credential keeps showing up in job postings.

According to Microsoft, the following applies: Experience using Microsoft Project 2013 and core project management concepts recommended. Certification policies do change from time to time, so confirm the latest requirements on the official exam page before you register.

Yes. VCETorrent offers a free 074-343 PDF demo so you can review the question style, difficulty, and explanations before committing to anything. After purchase, your Microsoft Managing Projects with Microsoft Project 2013 material includes 365 days of free updates, and if your product expires after that, you can extend the update service at a 50% discount from your member zone.

If you take the corresponding 074-343 exam within 60 days of your purchase and do not pass, you can apply for a full refund under our 100% Money Back Guarantee, subject to a few conditions: the failed exam must be the one matching your purchase; sitting the exam within 3 days of purchase does not qualify, since that leaves too little preparation time; downloading the material without actually taking the exam does not qualify; free materials and expired orders are excluded; and the candidate name must match the payer name. To apply, send a scanned copy of your enrollment slip together with your official Score Report (PDF) within 2 days after the exam, and claims are processed within 7 days. If you would rather not take a refund, you can exchange your purchase for two free products of equal value while keeping the update service on the product you originally bought. As for delivery, everything is an instant download: your products are sent to your email within one minute of payment — contact customer service if nothing arrives within 2 hours — and there is no limit on the number of computers you can install the software on.

The official Microsoft Managing Projects with Microsoft Project 2013 syllabus is organized into 5 main domains. The first three are Communicate Project Information, Manage Resources and Assignments, and Track and Analyze a Project. For the full domain-by-domain breakdown, see the complete Exam Topics outline above.

Microsoft Managing Projects with Microsoft Project 2013 Sample Questions:

Question #1

You are using Project Standard 2013.
You want the ability to see only tasks that have finish dates past their deadline date You need to achieve this goal using a custom field.
What should you do?

  • A. Use the Task Flagl5 custom field. Write a formula that compares the deadline date to the finish date, and set the result to Yes or No.
  • B. Use the Task Text30 custom field, also known as the Deadline Flag, since it automatically provides this capability.
  • C. Rename the Task Number1 custom field to Deadline passed. Write a formula that compares the deadline date to the finish date and displays Yes or No in the field.
  • D. Create a Lookup containing the values Yes and No against the Task Text1 custom field.
    Write a formula that compares the deadline date to the finish date and displays the correct value from the Lookup table.
Reveal Solution  Discussion  0

Correct Answer: A  🗳️

Question #2

You are managing a project using Project Professional 2013.
Your project schedule is showing task overallocation indicators in the Gantt chart view. You navigate to the Team Planner view to investigate more details regarding the over allocations.
You discover that the BA1 resource is overallocated and you need to see all assignments with details for BA1 to understand their current workload before making any assignment changes.
What should you do?

  • A. Click View, check Details, select Task Form then click on the BA1 resource.
  • B. Right-click the BA1 resource and select Information.
  • C. Click the BA1 resource and scroll to the end of the project.
  • D. Click View, check Details, select Resource Form then click on the BA1 resource.
Reveal Solution  Discussion  0

Correct Answer: D  🗳️

Question #3

You are a project manager who uses Project Standard 2013, and your task list includes a flag field that indicates, with Yes or No, if a non-summary task represents a physical deliverable.
Your project involves several tasks marked as deliverables, and management requires you to track how many deliverables are completed. The deliverable is considered completed when the Percent complete field is 100%.
You need to create a formula to calculate the total number of deliverables that are completed.
Which two steps should you perform? (Each correct answer presents part of the solution.
Choose two.)

  • A. Use the following formula: IIf([Physical Deliverable]=Yes And [% Complete]=100,1,0).
  • B. Set Calculation for tasks and summary groups to Count All.
  • C. Use the following formula: IIf([Physical Deliverable]=Yes And [% Complete]=100,0,1).
  • D. Set Calculation for tasks and summary groups to Sum.
Reveal Solution  Discussion  0

Correct Answer: A,D  🗳️

Question #4

You are a project manager who uses Project Professional 2013.
Your organization has been working with a new status report model for the last month. This new status report is created through the Built-in Dashboards and Reports in Project Professional 2013.
The standard Project Professional 2013 report views named Late Tasks and Milestone Report already have all the information required for the new model.
You are assigned to consolidate the information from these two reports into a dashboard view named Status Report Model. Your organization wants to keep the same format, colors, and layout.
You need to implement this solution.
What should you do?

  • A. Select all components on each view, and copy and paste directly to a new dashboard report.
  • B. Use the Burndown dashboard report to view this information.
  • C. Use the Organizer to merge the reports.
  • D. Use the Work Overview dashboard to view the data.
Reveal Solution  Discussion  0

Correct Answer: A  🗳️

Question #5

You are a program manager. Your project managers use Project Professional 2013 to manage projects. The project managers want to utilize the same resources across their projects.
You need to combine the projects, as well as the project resources, to see allocations across the projects.
What should you do?

  • A. Copy and paste all resource assignments into a Master file.
  • B. Share resources from an external resource pool.
  • C. Create a Master project and insert subprojects by using Link to project.
  • D. Open all projects in a new window.
Reveal Solution  Discussion  0

Correct Answer: B  🗳️

Viewing page 1 out of 22 pages.
Viewing questions 1-5 out of 110 questions.

5%

What Clients Say About Us

I'm really happy I choose the 074-343 dumps to prepare my exam, I have passed my exam today.

Hubery Hubery       5 star  

My friend introduces this website to me. Yeh, vaild dump. The service is very very good. Thanks to the 074-343 dump.

Avery Avery       4 star  

Passed my 074-343 certification exam recently using the exam answers by VCETorrent. Valid study material. Thank you VCETorrent.

Verne Verne       4 star  

The 074-343 pdf file was all that I needed to prepare for my exam. I did so well, its' unbelievable. VCETorrent thanks a lot for 074-343 exam practice questions.

Caesar Caesar       4 star  

The 074-343 training dump is a good study guide for the 074-343 exam. I studied the dump over and over, as they predicted that i passed the 074-343 exam. Thanks to all of you!

Rex Rex       4.5 star  

I faced 3 unexpected questions. But i managed to pass 074-343 exam, i recommend you to take the 074-343 exam material. It is enought to pass with it.

Diana Diana       4 star  

I am not surprised at I can pass the 074-343 exam. Because this material builds my confidence.

Lilith Lilith       4.5 star  

I wanted to write some words of gratitude about VCETorrent.

Yale Yale       5 star  

i confirm these 074-343 exam questions are still valid because i passed the exam in a perfect score.

Ellen Ellen       4 star  

Won my dream 074-343 certification!
Easy victory in exam 074-343!

Sally Sally       4 star  

I came to find that your guys are very kind. Then I decided to buy 074-343 exam dumps from you. I eventually passed the 074-343 exam. Thanks!

Herbert Herbert       4 star  

I passed the exam 3 days ago. The 074-343 exam Q&As are valid. It is the latest version that i bought.

Nicole Nicole       5 star  

Thank you team VCETorrent for the amazing exam preparatory pdf files. Prepared me so well and I was able to get HIGH marks in the Microsoft 074-343 exam.

Oswald Oswald       5 star  

I will inform you that I had passed the 074-343 exam this week. Thanks for your 074-343 practice exam! I will introduced your exam to my firend.

Stanley Stanley       4 star  

Valid 074-343 certification practice exam questions! Valid as always! I am a loyal buyer.

Novia Novia       4.5 star  

I can declare VCETorrent to be the best website available on the internet for certification exams preparations. Recommend to all of you!

Julia Julia       4 star  

LEAVE A REPLY

Your email address will not be published. Required fields are marked *

Try Before You Buy

Download a free sample of any of our exam questions and answers
  • 24/7 customer support, Secure shopping site
  • Free One year updates to match real exam scenarios
  • If you failed your exam after buying our products we will refund the full amount back to you.

Quality and Value

VCETorrent Practice Exams are written to the highest standards of technical accuracy, using only certified subject matter experts and published authors for development - no all study materials.

Tested and Approved

We are committed to the process of vendor and third party approvals. We believe professionals and executives alike deserve the confidence of quality coverage these authorizations provide.

Easy to Pass

If you prepare for the exams using our VCETorrent testing engine, It is easy to succeed for all certifications in the first attempt. You don't have to deal with all dumps or any free torrent / rapidshare all stuff.

Try Before Buy

VCETorrent offers free demo of each product. You can check out the interface, question quality and usability of our practice exams before you decide to buy.